Sectors & Projects - Commercial

Corporate Aviation Finishing Centre, Doncaster Robin Hood Airport

View inside hangar two
Outside view of hangar two
Inside the spray paint facility

Directions Finningley CIC

Key Features

  • Secure ‘airside’ environment
  • Design-build contract
  • Short mobilisation period

£2.5m Corporate Aviation Finishing Centre for the National Aviation Academy, based airside at Doncaster Robin Hood Airport. Building utilises cutting edge 4D spray paint booths to customise the interior and exterior of corporate aircraft.

Design and Build contract with heavy emphasis on short construction programme - customers were already booked in to use the facility and occupation by the Client on time was critical.

 Initial 6-week design period was reduced and an on-site start was achieved within 1 week of the order date. Collaborative working allowed quick mobilisation and helped us deliver a very tight programme on time and to budget.

Heavy emphasis on security and ‘airside’ working during the refurbishment of the existing hangar provided unique challenges for our site team.

"Good to see apprentice training being given."

Malcolm Palk, Considerate Constructors Scheme